  Hi,

 We are in standard costing, client has requirement where a product manufacturing cost would be $320 understand condition, in case of repairs, the product cost would be $50. Client wants to maintain the inventory to be maintained in this fashion 

Item A cost=320  on hand=100 units

Item A cost=50 onhand=20 units (because 20 units have been repaired)
 
Total inventory value= 33000 €
 
Goods once sold should take COGS as appropriate. Apart from creating a separate organization, any ideas or any costing method apart from Standard costing is welcome..
 
Thanks,
Anush N

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center