Planned value problem
i managing a planning whith following setting :
- Fixed duration and Units with Physical percentage complete
- Earned value calculated on actual plan
- Baseline planning is a copy with different budget manhour
- planning is periodic actualize by earned mh and actual mh
and i have some problem with planned value when i use earned calculation on actual plan and estimate to complete value in case i use baseline for calculation of earned value, in the 1st case i have good value for the estimate to complete, in the 2nd case i have good planned value.