I'm in the middle of the first 'test' run of an 11.5.10.2 -> 12.1.1 (eventually 12.1.3) Oracle apps instance.
The database has already been upgraded from 10.2.0.4 -> 11.2.0.1 with no issues.
I'm just at the stage where I'm laying down the new r12 filesystem
On the first server we have 1) database 2) main apps node for concurrent processing
On the second and third servers we have 1) apps node for web and forms processing.
The first node has been installed correctly with the filesystem laid down as I would expect (after a few changes and tweaks).
The conf_[SID].txt file also has all the correct information for the forms/web nodes.