OSP in OPM
Hi Gurus,
There is a process called and Ginning and Pressing which client performs via OSP.
The Process is as follows
1. Client purchases the Raw material i.e. Raw cotton from supplier
2. Client receives the Raw cotton in their inventory org and sends this raw material for outside processing where Ginning and Pressing operations are performed
3. After the OSP operation, The end result is Finished good cotton and bi-product as Cotton seeds and Gin jump .
i.e if 100 kg of raw cotton is purchased and the end product will be approximately 50% Finished Cotton and 40% Cotton seeds and 10% Gin jump.
Customer is trying to Map this process via OSP. Kindly suggest how to map this scenario.
There is a process called and Ginning and Pressing which client performs via OSP.
The Process is as follows
1. Client purchases the Raw material i.e. Raw cotton from supplier
2. Client receives the Raw cotton in their inventory org and sends this raw material for outside processing where Ginning and Pressing operations are performed
3. After the OSP operation, The end result is Finished good cotton and bi-product as Cotton seeds and Gin jump .
i.e if 100 kg of raw cotton is purchased and the end product will be approximately 50% Finished Cotton and 40% Cotton seeds and 10% Gin jump.
Customer is trying to Map this process via OSP. Kindly suggest how to map this scenario.
0