How Can we define setup time for component/Assembly
How can we define setup time for a job or groups of job in discrete manufacturing.
Does manufacturing scheduler consider setup time for Jobs.
for example.
For one injection molding machine we have required 6 hours to upload Mold on it.
1 hour production is 5,000 molded component on that injection molding machine.
its mean first job of 5000 components will tak 7 hours and after that all jobs will take 1 hour for 5000 molded componenet untill unless we have offload the mold form Injection molding machine.
How can we define this set up in Oracle Discrete Manufacturing.
Regards
Munawar Hasan