Y Axis UoM on Resource Profile
We have defined a material resource, given it a UOM of LF (linear ft). We pull up the Resource usage profile, and before we assign the resource to any activities, the Y axis correctly shows LF as the units. Great. Now, we actually assign the resource to a task (to which no other resource has been assigned). Before our very eyes, the UOM in the Resource profile changes from LF to h (hours). Anyone run into anything similar? I've tried and tried, but I can't get the UOM to be anything but hours once the resource is assigned to activities. Interestingly,