Selection of Alternative BOM´s
The Ct (Pharmaceutical) is implementing the decision rule: " use of alternative BOM´s" in Advanced planning on top of a Process Manufacturing Environmnent. They typically have up to 3 alternative recipes they can use to execute the Final Packaging activity. These recipes differ by the Bulk item nr that is used,
They would like to implement a set up where the recipe is selected that has Bulk on stock. Only after the stock is fully consumed, then it is accepted that planned orders for other recipes are created.
Any experience from anyone outhere on how to set up this functionality in the best possible way?