OSP Planning

edited Feb 16, 2016 4:06AM in Value Chain Planning - EBS (MOSC) 8 commentsAnswered
 All,

How can we achieve the OSP Planning in ASCP. As per my research in the metalink and Service request, oracle not supports the OSP planning in ASCP. How the other business people are handle the below scenario in their implementations.

Scenario:

The Demand Item FG_ITEM_A ( forecast/Sales order) will have routing with two opertaions. First operation is attached with OSP Resource 1 and second operation is attached with OSP resource2.

Once the planner releases the planned order for FG_ITEM_A from planning work bench. it creates work order in the oracle WIP module, once the mfg planner releases the work order from WIP module, it should create requisition for the OSP resourec1 ( FG_ITEM_RESOURCE1_A), FG_ITEM_RESOURCE1_A item is attached to the OSP Resource1.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center