Detail scheduling of planned order with time stamp.
we have a business scenario, for the buy items ASCP suggested planned orders on a daily basis.. but the business requirement is instead of receive all the purchase orders on the same day and time, they would like to receive the purhcse orders first PO morning, second PO is noon, third PO is evening. they want to add time stamp on the PO with diffrent timings due to unavailability of material storage
Detailed Scenario:
FG1 is the Finished good
ING1 is the Ingredient for FG1.
1)Craeated a batch for FG1 with Quanity 10000 Cases with start date as 10-Apr-2011 10:00:00 AM and End Time is 8:00:00 PM.