Changing resource organization on a resource in workplan
We created a project with a Project owning organization A which is not in a burden schedule (hierarchy).
Because of this Raw cost and Burdened cost are the same.
We created a plan in workplan with 133 tasks.
Then we saw that we where using a wrong Project owning organization and changed it to Project owning organization B which is in a burden schedule
using Mass update which changes the organization for the project and tasks.
This does not change the organization on the resource and burden cost is not recalculated.
If we delete the resource and reinsert it then the new organization B is used and burdened cost is calculated using the burden schedule.
We created a plan in workplan with 133 tasks.
Then we saw that we where using a wrong Project owning organization and changed it to Project owning organization B which is in a burden schedule
using Mass update which changes the organization for the project and tasks.
This does not change the organization on the resource and burden cost is not recalculated.
If we delete the resource and reinsert it then the new organization B is used and burdened cost is calculated using the burden schedule.