P6 Help Resources Usage
Please advise when resources usage is calculated for forecasting until project completion, total remaining units are estimated
based on 1. (Budgeted - Actual Qty)
or
2. (Budgeted - BudgetedxActivity % complete). Question is which takes the precedence in calculation when as-built data i.e. Actual dates and Activity % complete have been loaded to the program. Consider calculation type is based on Retained Logic with Duration based.