Try to reverse Capitalize PA interfaced asset.

edited Apr 28, 2011 4:25AM in Fixed Assets - EBS (MOSC) 3 commentsAnswered
  Hi All

 

I hope I can get advice and feedback on workaround to resolve this issue.

 

  1. 5 Assets were mistakenly created in PROJECT and because the TASK is assigned (added) with that specific asset – so all the 5 new Unassigned assets when generated and interfaced to Assets – they were created and ‘locked’ to that Asset.

 

  1. I do not want to Reverse Capitalize because that will reverse ALL the past transactions for that Asset.

 

Is there a way to revert the assignment and revert back the CIP amount as if not being assigned?

 

I have tried to assigned and interface to Asset and in Prepare Mass Addition screen – I will remove the asset and then Add to Asset to an existing simple asset, then tries to Reverse Capitalize.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center