ETC Cost

edited May 20, 2011 3:06AM in Projects - EBS (MOSC) 3 commentsAnswered
 Hi, could you please confirm if the following is true for workplan functionality:

Planned 200hrs @100/hr=$20,000
Actuals 10hrs @185/hr=$1,850


System calculates:
ETC Effort 190hrs (Correct)
ETC Cost $18150 (Incorrect)
EAC Cost $20,000 (Incorrect)


Should be: ETC Cost 190hrs @100/hr=$19,000
Should be: EAC = $20,850

Thanks!