ETC Cost
Planned 200hrs @100/hr=$20,000
Actuals 10hrs @185/hr=$1,850
System calculates:
ETC Effort 190hrs (Correct)
ETC Cost $18150 (Incorrect)
EAC Cost $20,000 (Incorrect)
Should be: ETC Cost 190hrs @100/hr=$19,000
Should be: EAC = $20,850