Capacity Planning

edited Aug 17, 2011 10:57PM in Manufacturing - JDE1 (MOSC) 6 commentsAnswered
My understanding is that the F33133 capacity buckets are derived from the Past Due Periods and Planning Horizon Periods defined in the R3482.

We manually run R3382 daily just a few hours after MRP completes, however, we notice that the Capacity buckets and the Time Series buckets are not always the same until later in the day after the Capacity Plan has been submitted several times. Generally, the Past Due of P3313 do not align with the Time Series in that one Past Due is not in the table and/or the first period may be combined with the second period.