ATP Inquiry - Understanding ATP results

edited Jun 9, 2011 7:34AM in Value Chain Planning - EBS (MOSC) 5 commentsAnswered
 Hi All,

Using ASCP for ATP. ATP results are not as expected. Any pointers on the same will be helpful.

Part A(Make) has Part B(Buy) as only component. On-hand for A is 1. A PO for B, 1 Qty, is in place on 15th Jun as delivery date. B has got a lead time (Pre+post+process) of 22 Days. A has got a lead times of 5 days fixed and 0 days Variable. Ran a plan today 8th Jun. When doing an ATP Inquiry for 3 Qty. The recommendations are as follows:

On requested date i.e., today, 1 Qty is available.  - This is from on Hand - Result is as expected