 Scenario:

Two resources are assigned to an Operation (Machine and Labor). These two machines work simultaneously to perform theoperation.

Routing setup:

In Operation resources window resoruces are defined as bellow

seq   resources code   Basis  Rate  schedule seq number   schedule Flag

10      Machine               Item    1            10                                 Yes

 20     Labor                   Item     1            10                                 Yes

When creating a job and running ascp planning these resources are scheduled in series instead of being simultaneous reosurces.

Somebody told me about profile option! Any update on this issue.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center