 Hi All,

We are using R12.0.6 OPM.
we have a scenario like bellow:-

We are producing PRODUCT (FG1) using intermediate item(W1)
and item W1 is produced using item R1 and item R2.

After selling the product (FG1) sometimes customer return the product(FG1)
to us due to some reason.After sorting of those return product, part of the return FG1 item
used to produce the item (W1). This W1 again used to produce the FG1.

FG1(P) = W1(Ing)
W1(P) = R1(Ing) + R2(Ing)

after customer return:-
W1(P) = FG1(Ing) (here qty of FG1 is more than W1)

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center