Hi,

We are assigning material items to the workplan tasks while creating WBS in Project Management.

But material items(inventory items) from the inventory organization does not show cost in the workplan planned cost. We are only able to assign quantity of material items.

Please let us know how the frozen cost of inventory items from Inventory will flow to Project workplan in PJT.

Thanks in advance.

Regards,

Rajan