Resource Availability during resource leveling

edited Jan 10, 2012 6:15AM in Primavera (MOSC) 1 commentAnswered
When leveling in Primavera 6, are resources only made available when the activity calendar and the resource calendar intersect?  In other words, if there is an activity with only one resource:

If the activity calendar is working day shift only, but the resource calendar is working day and night shift, then the activity will be scheduled on days only. 

If the activity calendar is day shift and night shift, but the resource calendar is day shift only, then the  activity will be scheduled on days only.

Only if the activity calendar and the resource calendar are day shift and night shift will the activity be scheduled for both days and nights?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center