Mass update of new cost burdened rate schedules to existing projects and templates
Currently we have two open rate burdened cost schedules. One is using hierarchy #1 (from HR), and the other is using hierarchy #2. I have ran some test using projects pointing to both hierarchies. So far things are processing normally.
To simplify things for reporting issues we would prefer to use one cost burdened rate schedule. Currently all open projects and templates are pointing to hierarchy #1. Is there a mass update function that would update these projects and templates with the cost burdened rate schedule for hierarchy #2? Also through preliminary testing it looks like I would have to update the cost burdened schedules at both the project and task levels. I ran into this problem when the organization information was changed in hierarchy #2. Thanks for your help.