Planned Order Release - WIP Job start date

edited Aug 2, 2011 8:01AM in Value Chain Planning - EBS (MOSC) 9 commentsAnswered
Hi,

I need your help to understand how WIP start date gets calculated when you release a planned order from PWB.

In the test case which I executed, suggested order date in PWB is 21-JUL-2011 00:00:00 where as when I convert the Planned order to WIP job, the start date is 20-JUL-2011 14:00:00

It is surprising to me. It indicates, Job is already delayed by 1 day. would be interested to know your views on the observation. Your views will enable me to fix this issue at the earliest. 

Lead Time for your reference - Preproc - 0. Proc - 1, postproce - 0, fixed -0, var - .047619. PLO qty = 10

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center