Resource usage profile does not match remaining early dates
See attachments.
Activity named "HOTBOLT BODY JOINTS" has Remaining early finish of May 9 17:00. The "remaining work" bar on the chart shows it finishing at 17:00.
The resource usage profile for remaining early units shows the resource "PF" working until 20:00. Why is there a difference?
The screen print on the attached shows that finish, early finish, and remaining early finish are all the same.