Resource usage profile does not match remaining early dates

edited Jul 28, 2011 5:08AM in Primavera (MOSC) 2 commentsAnswered ✓
I will be leveling resources for a turnaround, and the important start and finish dates to us will be the dates after leveling.  The "remaining early dates" are supposed to be the ones that take leveling into account, but there seems to be a discrepancy.

 

See attachments.

Activity named "HOTBOLT BODY JOINTS" has Remaining early finish of May 9 17:00.  The "remaining work" bar on the chart shows it finishing at 17:00. 

The resource usage profile for remaining early units shows the resource "PF" working until 20:00.  Why is there a difference?

The screen print on the attached shows that finish, early finish, and remaining early finish are all the same.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center