Comparative Dates from the Baseline Schedule
I created a baseline schedule by copying a previuos file then converting it to a baseline project file. I then assigned it as the "Project" and "Primary" baseline in my current project schedule file. I created a layout that contained columns for the "Start" and "Finish" dates from my current schedule and the "BL Start" and "BL Finish" dates from the Project baseline. The BL dates are not correct. It appears that the "Planned" dates are showing in the BL dates. Does anyone have a suggestion as to what I may be doing wrong?