MPS not taking open WO in consideration
Hi everyone,
We have set up a system with 3 Branch Plants: (A) as a warehouse where we input SO, (B)as a production site to manage supply (WO), and (C) to regroup demand for MPS, where we generate the MPS messages.Our problem however is that open WO are not taken in consideration when calculating our needs.
If we have a new SO and no stock (neither in A or , we'll get the message to open WO. After opening the WO, we still get the same message again.
We have set up a system with 3 Branch Plants: (A) as a warehouse where we input SO, (B)as a production site to manage supply (WO), and (C) to regroup demand for MPS, where we generate the MPS messages.Our problem however is that open WO are not taken in consideration when calculating our needs.
If we have a new SO and no stock (neither in A or , we'll get the message to open WO. After opening the WO, we still get the same message again.
The system takes in consideration the stock of B but not the open WO. I have checked supply demand inclusion rules (P34004), they include WO. Branch relationship (P3403T) has check availability selected.