 Dear Team,

    While running DBUA for recompiling invalid objects can we select  the 'Degree of Parallelism' to more than 1.

   Does it have any issue if we select this to more than 1.

  Or should we play safe and select only 1.

  Cause i did the upgrade of my 9i db in our test instance of EBS 11i and it took 40 hrs to finish.

   It took around 30 hrs for compiling invalid objects.

   Please advice.

Thaks & Regards,

     Aarif

 

 