Hi all,

 

This is a Primavera P6 Version 7.0 CPM stand alone Cost loaded schedule. The cost is loaded only on the resource tap with dollar amount in the budgeted field only. Since I just started the schedule so there is no stored period performance before.  I did e-mail the CPM XER file to the PM to check it out but when he opened the file it did not have valued for the resources. All budget value for the resources is $0.00.

My question is how to e-mail the CPM and with money on the resources?

 

Thank you,

 

Ashraf.

.