Project Expenditures - How to tie the IPV from backend

edited Dec 13, 2011 12:38AM in Procurement - EBS (MOSC) 1 comment
Hello

Without PJM, we have PO inventory receipts tied to a project (expense PO distribution). exploring the below option..

1) I created the PO receipt transaction in pa_expenditure_interface and imported the PO receipts. Distributed the costs ..So far so good...
2) Now when there is variance on the AP invoice, PRC: Interface suplier costs (Invoices - Yes) is interfacing the full AP invoice amount as cost....

I want to know the link which ties the transaction so that PRC:interface supplier costs brings only the IPV to project expenditures....basically need the technicall link how Oracle ties PO to AP via project expenditures to customize...

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center