edited Dec 27, 2011 1:02PM in Hyperion Essbase (MOSC) 13 commentsAnswered

Hello,

 

Has anyone successfully implemented active-active (fail over + load balance) essbase cluster (in any version)

 

We are in process to setting up essbase active-active cluster in version 11.1.2.1 but ran into a challenge. How to keep both the cubes in sync becomes a challenge. (Linux servers)

 

I have tried replicate partition ( ut it do not work for ASO cube), export then load (takes too much time to export  an cube with 25 g of ASO data) , load cubes on both servers at the same time (Oracle data I/o Issues which causes the 2nd cube build to take about 3 times longer since we are using sql interface and we don't have to change our existing process to load data files instead because there are way too much involved with our deadline).

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center