Costing for Proj Mfg cost enabled Org - Issue

edited Nov 30, 2011 4:51AM in Cost Management - EBS (MOSC) 3 comments
1) Received Proj Manuf PO in project locator and receiving transaction processor completed normal. I need to run cost collection and import this cost to Projects.

2) Defined item cost and ran Cost udpate for the new item in new org. completed normal.

3) CMCCCM module: Cost Collection Manager is not picking the material transaction.

COSTED_FLAG, cost_update_id are blank. pm_cost_collected is "N".

What process/steps am I missing for PO receipt inventory cost to interface to Oracle Project expenditure item for source "Inventory"?

 

Thank you