Charge hours to workplan task instead of financial task
Dear All,
We are implementing Projects and OTL modules along with other financial modules in R12.1.3 implementation.
At this point - the work and financial plans in Projects are not fully shared therefore the tasks are not the same. We have a requirement to charge hours to workplan task instead of financial task in OTL. But OTL shows only the financial task in the Tasks LOV.
Few options we have are:
a. make the work and financial workplan as fully shared.
Pros: easy to implement
Con: complex financial structure
b. use DFF for the workplan tasks in OTL.
Pros: 1. simple financial structure (i..e not fully shared)