PM runs quite slow
We use the Primavera PM6.2 for a project ,and set different level projects.
A new project created by copy from the baseline project., and update the process , the PM frozen, I cann't edit it .
We have opened the project and the data is loaded 100%,but the activity windows can not be load,the PM is frozen about 30minutes.
After opened it ,we check the project integrity,the report as beow:
help me by email : mf20070425@126.com.thanks a lot.
54. Check Activity for: Completed activity Actual Start Date = Null
>>>Errors:
Activity: MGENOOOO0130 - Not Fixed: Set activity Actual Start Date = Planned Start Date