outside manufacturing without manufacturing module
Required to configure company practice of issuing raw material according to Recipe to contractor to manufacture End product for the company which has no manufacturing facilitiy. Company is using Financial / supply chain( Procurment , Inventory , Sales order managemnt , Transport management moudles) .
work around for the situation as follows;
1. issued material using Inventory issuance to charge cost to WIP account. using subledger as vendor address to tracking purspose.
2. generate PO for End product which will be at vendors rate ( Cost )
3. Recieved End item and apply landed cost for Material and reduce WIP as well as charge to End item cost.
Need suggestion
work around for the situation as follows;
1. issued material using Inventory issuance to charge cost to WIP account. using subledger as vendor address to tracking purspose.
2. generate PO for End product which will be at vendors rate ( Cost )
3. Recieved End item and apply landed cost for Material and reduce WIP as well as charge to End item cost.
Need suggestion