Hello,

If anyone has a solution or suggestion for this scenario it would be greatly appreciated: 

Scenario: 

  • Metal fabrication business who consumes partial lengths of steel, e.g. 6 metre length 10mm Rod. 
  • Current primary unit of measure is M (metres). 
  • The item is stocked in a unit of measure EA (each) where 1 EA = 6 M. 
  • When using this material only 5.5 M is used therefore 0.5 M is still in inventory. 
  • After consuming 12 x 5.5 M on other work orders JDE thinks there is 6 M or 1 EA in stock. 
  • An open order exists which requires 5.5M, MRP runs and sees that 6M is in stock therefore will not order any more.  In reality there are 12 x 0.5M lengths not 1 x 6M length. 

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center