Create Financial tasks in MS Project and send to Oracle Projects - transaction dates are always used

edited Dec 1, 2011 5:52AM in Projects - EBS (MOSC) 1 commentAnswered
 When create financial tasks in MS Project - start and end dates are required.
When send from MSP to Oracle: these dates become Transaction start date, Transaction finish date for every financial task.

But I do not want to set transaction dates at all - our customer do not use this functionality.

We use not-shared, no mapping financial and workplan structures.
We use Release 12.1.4

How to  save from filling transaction dates ?