Capacity Planning with ASCP and OPM
We are focussing on the resource-level Horizontal Plan in the planning workbench.
What we have learned is that each resource has its capacity (Available Hours) calculated as follows: Hours X Count. Where "Hours" is the time on shift from the organization calendar, and "Count" is the number of that particular resource equipment we have, from the count field on the resource setup (in an OPM responsibility: Route SETUP > Plant Resources).