Hi All,

We have a requirement to have a Sales order Number reference in Discrete Job which is created through the Planned Orders from either ASCP/MRP workbench.

Demand input for planning is Forecast which has a Project attached to it. Later when there is a Sales order confirmed from the customer, the requirement is to have this Sales Order linked to the Discrete Job.

Sequence of activities:

1) Forecast created for the assembly and the project no is attached to the forecast

2) Forecast attached to the Plan (ASCP/MRP)

3) Launched the planning process

4) Discrete Job created from the Planned orders through ASACP/MRP workbench

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center