How can I get information held as an Activity UDF to show on my resource assigments tab? Primavera P
It seems to me that there is no way for me to get the reference numbers I require to show on the resource usage spreadsheet.
Is anyone aware of a way to copy the values an Activity UDF to a Resource Assignment UDF? I have 500+ projects with around 50000 activities where a unique identifier is held in a UDF and desperately need to get these references to show up against the assignments in the resource usage reports
Any held would be greatly appreciated!
Kind Regards,
DC
Is anyone aware of a way to copy the values an Activity UDF to a Resource Assignment UDF? I have 500+ projects with around 50000 activities where a unique identifier is held in a UDF and desperately need to get these references to show up against the assignments in the resource usage reports
Any held would be greatly appreciated!
Kind Regards,
DC