Approval processes does not stop with approver
I have an issue with the PO Approval processes. The approver Mr.X has a limit of 30,000 but the PO for a value of 25,000 does not get into Approved status even after Mr.X approves it; instead, it goes furhter in the line, and goes for the approval for Mr.Y, the boss of Mr.X.
I have checked the approval assignments and approval groups. All seem to be fine. I ran the script providved by oracle to reset the PO into Incomplete status, and tried approvals again. But it does not work.
Please somebody given me an answer for this.