How to view the Future dated SR's and Tasks in the UMP, when we have the Current SR and task open an
We are using the CMRO do address the Preventive maintenance (PM) functionality using Service contracts and Field service.
That is we are using CMRO to the bare minimal, as needed for the PM functionality.
We have a Service agreement spanning say 3 yrs for a serial number - customer combination.
we have the coverage template associated to the PM Program / schedule which would create a task every 3 months for a PM visit.
when we run the "Preventive Maintenance Generate Service Requests and Tasks" say for 1500 days and run the "Preventive Maintenance Update Unit Maintenance Plan", we observed that only current or next due SR is seen in the UMP.