After WIP material return and osp return net activity shows negitive value, is it possible to correc
Job = OSP
We did all transaction like Material Transactions, Move transaction and OSp transactions in Mar-2011.
From this Job we return the material in the same date after 10 or 15 days.
Incurred cost and cost relieved also return, but due to average cost change in this time period, in WIP Value summery the Nett activity is showing in negitive.
Can any one tell me is it possible to right off this negitive value from from WIP value summery of that particular job.
Regards
Kapil