Does the Qty required need to equal the qty issued on a work order parts list if the some of parts a

edited Nov 19, 2015 10:00AM in Manufacturing - JDE1 (MOSC) 3 commentsAnswered
Example.  Work order issues calls for

64pcs from lot A

We issue 50pcs from Lot A

86pcs from Lot C

We issue 100pcs from Lot C

In theory, since the total qty issued = 100 and the total Required  = 100 shouldn't the demand be considered satisfied? 