How to transfer project cost of inventory to project
Hi, there
I created a Purchase Order with destination of inventory and associated with project and task. After approved, I received goods of the PO to a project loactor.
I don't know what to do next so that I can see cost of the receipt updated to the PSI.
My step:
1. run the cost processor
2. run the PRC: Transaction Import (Parameter:inventory)
3. run the Update Project Summary Amounts
But it doesn't work. It only works when I do the Miscellaneous issue to a project.
2