In my example below I have setup the "Asset Grouping Method: All" and the Grouping Level as per following detail for Project A executed to produce Asset X and Asset Y
- Capital Task 1 Assigned to Asset X
- Capital Task 2 Assigned to Asset Y
- Capital Task 3 Assigned as "Common Cost"
Expenditure Items
1) Project A, Task 1, Expenditure Type W $10000
2) Project A, Task 1, Expenditure Type W $2000
3) Project A, Task 1, Expenditure Type Z $5000
4) Project A, Task 3, Expenditure Type W $6000
When the PRC: Generate Asset Lines is run my understanding is that will occur the following: