 Hi,
I want to confirm with an example the concept of Grouping Method, Grouping Level and Unassigned Costs.

In my example below I have setup the "Asset Grouping Method: All" and the Grouping Level as per following detail for Project A executed to produce Asset X and Asset Y

- Capital Task 1 Assigned to Asset X

- Capital Task 2 Assigned to Asset Y

- Capital Task 3 Assigned as "Common Cost"


Expenditure Items

1) Project A, Task 1, Expenditure Type W $10000

2) Project A, Task 1, Expenditure Type W $2000

3) Project A, Task 1, Expenditure Type Z $5000

4) Project A, Task 3, Expenditure Type W $6000

When the PRC: Generate Asset Lines is run my understanding is that will occur the following:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center