Outside processing jobs

edited Mar 7, 2012 7:42PM in Discrete Manufacturing - EBS (MOSC) 7 comments
Hi,

I created an OSP item, created and OSP resource for it, an OSP department, and in the routing I attached the department and the OSP resource to that department.

in WIP parameters the requisition creation time is 'At Operation' but when the quantitiy is move to the queue of the operation no requisition is getting created also I am not able to see any record in PO_requisitions_interface_all table and hence it was not picked up by the import requisition program to create a requisition.

can any one please tell me when the records are inserted into PO_requisitions_interface_all table or else what can be the reason for requisition not getting created?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center