cost management should not have impact in back to back order process
Hi Folks,
We have following requirement.
Costing information
Ex:- We have Item= iphone cap,
one item Cost= 10,
Available Qunatity=10
Total costing= 100,
Costing Method: Average
We got an customer order for 20. now we split this order into 2 lines.
Line -1 for qunatity-10 (We used the available quantity)
Line-2 for Quantity-10, we raise a PO for 10 @ one item cost=11
Receive the Items 10 @ cost of =10 ,
now Receiving Account (Debit) 110
Inventory Accrual (Credit) 110
when we deliver the receipt into inventory.
Inventory Valuation (Debit) 110
Receiving Account (Credit) 110
My costing will be updated as follow.
Costing information
Ex:- We have Item= iphone cap,
one item Cost= 10.5
0