WIP job not getting operations from phantoms
We are having a problem with the scheduling of WIP jobs for a top level item containing phantoms. The bill of material looks like this:
Top Level Assembly
-Phantom 1
--Component A
-Phantom 2
--Component B
The Top Level Assembly does not have a routing, but this problem exists even when a routing is defined. Phantom 1 has a routing with a scheduled resource of 5 days. The BOM Parameters are set to Use Phantom Routings and to Inherit Phantom Op Seq. Creating a Discrete Job for Phantom 1 results in a completion date 5 days after the start date. Creating a Discrete Job for the Top Level Assembly results in a completion time = start time.