Consumption of CTO Forecast in ASCP
I wanted to understand how and at what level forecast consumption happens in a CTO environment in ASCP.
Consider the following example
MODEL 1
-OPTION CLASS
--OPTION A (Planning Per - 60%)
--OPTION B (Planning Per - 40%)
Now lets say there is a Sales Order of qty 20 for MODEL1 and Org and DC.
On using the Configurator in Oracle Ebs, we select OPTION A and then Progress Order to create a star item say
MODEL 1*234.
Now in the above scenario, the questions I have are:
1) At what level should I maintain forecast in Forecast set, so that the consumption happens in ASCP.