WBS Summary Duration Totals are Incorrect

edited Apr 3, 2012 2:42AM in Primavera (MOSC) 2 comments
Why is the WBS Summary duration using a 5 day calendar, yet all the activities within that WBS are assigned a 7 day duration, it is skewing the summary totals duration from 7 day totals to a 5 day total?