P6 v7 earned value not working as expected.

edited Mar 20, 2012 4:40AM in Primavera (MOSC) 1 commentAnswered
I’ve got a curious situation with the earned values not matching the baseline when I’ve set the “current project” as the baseline.

 

A little background on my P6 file to help pinpoint what I’ve been missing;

It is budget loaded by activity, but no resources assigned.

We are using the “Actual Labor Units” to match the “Earned Value Labor Units” so the “Units % Complete” match the “Physical % Complete” reported by the discipline leads.

There is no “negative float” in the schedule.

 

Here are the steps I’ve completed in checking;

Verified/adjusted that each activity the “At Complete Labor Units” equal the “Budgeted Labor Units”

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center