P6 v7 earned value not working as expected.
A little background on my P6 file to help pinpoint what I’ve been missing;
It is budget loaded by activity, but no resources assigned.
We are using the “Actual Labor Units” to match the “Earned Value Labor Units” so the “Units % Complete” match the “Physical % Complete” reported by the discipline leads.
There is no “negative float” in the schedule.
Here are the steps I’ve completed in checking;
Verified/adjusted that each activity the “At Complete Labor Units” equal the “Budgeted Labor Units”