Cost Allocation to Assets at a Task
Consider the following scenario In Project A ,
Asset Cost Allocation Method = Spread Evenly
Group Method = Expenditure Type
An Asset A1 is created and assigned to the Task T1
Accumlate the CIP cost at Task 1
Then Run the Process "PRC: Generate Asset Lines for a Single Project"
When the process is finished the asset lines are generated and cost lines are assigned to asset A1.
Then Run the Process "PRC: Interface Assets to Oracle Assets" so the Asset A1 is interfaced to
Oracle FA
In Oracle FA RUn "Post Mass Addition
Next month a new Asset A2 is created and assigned to the Task T1
Asset Cost Allocation Method = Spread Evenly
Group Method = Expenditure Type
An Asset A1 is created and assigned to the Task T1
Accumlate the CIP cost at Task 1
Then Run the Process "PRC: Generate Asset Lines for a Single Project"
When the process is finished the asset lines are generated and cost lines are assigned to asset A1.
Then Run the Process "PRC: Interface Assets to Oracle Assets" so the Asset A1 is interfaced to
Oracle FA
In Oracle FA RUn "Post Mass Addition
Next month a new Asset A2 is created and assigned to the Task T1
0